Hard-wearing commercial laminate through a New Town primary school corridor.
Portfolio Case Study

New Town Primary School: Laminate Through a Term Break

Nine hundred square metres of commercial laminate through corridors and classrooms in a two-week term break.

Project Category
Commercial Education
Location
New Town, TAS
Material Selection
AC5 Commercial Laminate
Installation Time
12 Days

The Challenge & Vision

Two weeks, no extensions, and 900 square metres across nine classrooms and the main corridor spine. Term dates do not move. The floor also had to meet the department's slip rating for a school corridor and survive a decade of trolleys, chairs and a great deal of running.

Commercial laminate being laid along a school corridor during the term break.
Two crews working from opposite ends of the school corridor spine.

The Solution

Two crews worked from opposite ends of the corridor spine and met in the middle on day eight, with classrooms completed in parallel behind them. We specified AC5 commercial laminate — the grade above what a school brief usually calls for — because the replacement cost of a second term-break shutdown dwarfs the material difference.

Total Area
900m²
Total Area
Delivered In
12 Days
Delivered In

Specified Above the Brief

  • AC5 Commercial

    A grade above the brief, because a second shutdown costs more than the material.

  • Slip Rated

    Meets the department's corridor requirement in both dry and wet states.

  • Two Crews

    Parallel working is what turned a three-week job into a twelve-day one.

Project Details

Client
New Town Primary School
Location
New Town, TAS
Total Area
900 sqm
Timeline
12 Days in a Term Break
Material
AC5 Commercial Laminate

Project Roadmap

Twelve working days inside a fourteen-day term break, with two days in hand.

  1. Day 1: Audit

    Slab moisture tested across all nine classrooms and the corridor spine.

  2. Day 2–3: Prep

    Old vinyl lifted, slab ground and levelled ahead of the two crews.

  3. Day 4–10: Fit

    Corridor worked from both ends inward, classrooms completed in parallel.

  4. Day 11–12: Handover

    Trims fitted, full clean, and sign-off two days before students returned.

Inspired by this project?

Tell us about your space and we will walk you through the options, the timeline and the cost.